Sample Question:
What is the percent of completion to the nearest 10th of a percent? The cost to date is $86,461.24. The estimated cost to complete is $34,950.00 on a contract for a job sold for $140,000.00.
A. 61.8%
B. 71.2%
C. 73.6%
D. 68.0%